District wise Namami Gange STPs Status

Sr. No. Name of Town/District Name of STP Project Name Design Technology Capacity of STP (MLD) Design Parameter Inlet Parameter Outlet Parameter Influent (MLD) %age Utilization Agency Maintaining the STP Functional / Non-Functional Compliant / Non-Compliant Updation Date
BOD TSS BOD COD TSS BOD COD TSS
1 Prayagraj Kodra 1. Sewerage & Non-Sewerage schemes for Pollution abatement of River Ganga at District-'B' & 'E' of AllahabadSewerage & Non-Sewerage schemes for Pollution abatement of River Ganga at District-'B' & 'E' of Allahabad - 85 MLD HRBF 25.00 <20 <30 135 328 261 13 36 21 25.47 MLD 102% M/s Prayagraj Water Pvt. Ltd. (Adani) Functional Compliant 17-04-2021
2 Prayagraj Numayadih HRBF 50.00 <20 <30 135 320 264 15 40 28 9.94 20% M/s Prayagraj Water Pvt. Ltd. (Adani) Functional Compliant 22-05-2021
3 Prayagraj Ponghat 10.00 <20 <30 132 296 248 15 40 23 7.134 71% Prayagraj Water Pvt. Ltd. (Adani) Functional Compliant 06-05-2021
4 Prayagraj Naini - 2 2. Sewerage & Non-Sewerage schemes for Pollution abatement of River Ganga at District-'A' of Allahabad ASP 20.00 <30 <50 163 360 335 19 36 35 15.68 MLD 78% M/s Prayagraj Water Pvt. Ltd. (Adani) Functional Compliant 22-05-2021
5 Prayagraj Salori - 2 3. 14 mld STP at Salori, Allahabad SBR 14.00 <10 <10 104.4 271 257 7 20.2 7.2 14.449 103% M/S Toshiba water solutions prayagraj Functional Compliant 12-06-2021
6 Varanasi Varanasi GAP-II (JICA) 4. JICA assisted Ganga Action Plan Phase-II Project at Varanasi (EAP - JICA) Construction of 140 MLD STP at Dinapur ASP 140.00 20 30 105 223 198 14 30 20 81.32 58% VA-Tech Wabag Functional Compliant 25-05-2021
7 Garhmukteshwar Garhmukteshwar-I (NGRBA) 5. Sewerage system & STP works - 9 MLD UASB 6.00 < 20 <30 184 227 195 14 45 17 3.45 58% M/S Anandilal lalpuria Functional Compliant 18-05-2021
8 Garhmukteshwar Garhmukteshwar-II (NGRBA) UASB 3.00 < 20 <30 176 196 185 10 55 18 .50 17% M/S Anandilal lalpuria Functional Compliant 18-05-2021
9 Moradabad Moradabad (NGRBA) 6. Sewerage system & STP works (Phase I ) UASB 58.00 < 10 < 10 135 310.5 260 6.0 28.8 8.5 26.9MLD 46% L&T; Functional Compliant 14-03-2021
10 Kannauj Kannauj (State/ NGRBA) 7. Sewerage system & STP works (Phase II) SBR 13.00 <10 <10 109 290 286 8 74 9 9 69% UPJN Functional Compliant 10-06-2021
11 Narora Narora (NGRBA) 8. Sewerage scheme at Narora, Bulandshar UASB 4.00 < 10 <30 149 293 290 4.98 25.2 25.1 2.256 56% M/S EMS Infracon Functional Compliant 06-06-2021
12 Anupshahar Anupshahar (NGRBA) Zone A 9. Sewerage Works in Anup Shahar, Buland Shahar - 2.5 MLD UASB 1.50 < 10 < 10 189 270 305 10 32 10 1.489 99% LC Infra Projects P Ltd. Functional Compliant 06-06-2021
13 Anupshahar Anupshahar MBBR 1.00 < 10 < 10 123 284 208 8 18 8 47.8 4780% Functional Compliant 03-06-2021
14 Bithoor Bithoor STP 10. Sewerage scheme and STP at Bithoor Kanpurnagar, (UP) - 2.40* 0 0 0 0 0 0 0 0 NGRBA Functional Non-Compliant 03-06-2021
Grand Total
347.9 293.188 84%